Follow us on Google Get our news on Discover Follow

A 1,050-ton slab at the bottom of a 115-foot Ontario shaft is the foundation of the Western world’s first grid-scale small reactor, and the 300-megawatt machine meant to stand on it will now be late, because its engineering is still being finished as the concrete goes in

A 1,050-ton slab at the bottom of a 115-foot Ontario shaft is the foundation of the Western world’s first grid-scale small reactor, and the 300-megawatt machine meant to stand on it will now be late, because its engineering is still being finished as the concrete goes in

{{author_name}}

Luis Reyes

Nov 16, at 11:00am ET

Anyone who’s had a kitchen remodeled knows the rule. You finish the drawings, you order the cabinets, and only then does somebody start knocking out walls. Do it in the other order and you wind up paying a crew to stand around while the plans catch up.

Ontario Power Generation is finding out what that rule looks like when the kitchen is a nuclear reactor.

On November 10, the province’s government-owned utility said the first small modular reactor at its Darlington site, east of Toronto, is no longer expected to hit its October 2030 commercial operation target. It also won’t come in under the C$7.7 billion it had previously disclosed for Unit 1, which World Nuclear News converts to about US$5.4 billion. That figure covers the reactor plus systems and services the other planned units would share.

You may remember this hole in the ground. Back in July, we covered the 1,050-ton slab OPG lowered to the bottom of a 115-foot shaft at Darlington in April, and later the steel reactor vessel taking shape for it in an Ontario factory. That slab is still down there. The 300-megawatt machine it’s supposed to hold up is what’s running late.

So what went wrong?

According to OPG’s third-quarter results, the problem is engineering that isn’t finished yet. The reactor is a BWRX-300, designed by GE Vernova Hitachi, and nobody has finished building one yet. That’s what “first-of-a-kind” means here. OPG says the supplier’s ongoing engineering for a first-of-a-kind design is affecting both how construction gets done and how the supply chain performs.

OPG CEO Nicolle Butcher put it plainly in the release, saying “we have identified risks that will impact Unit 1’s schedule and budget.” She also said the utility will share more as the work moves along.

GE Vernova Hitachi sees it a bit differently. A spokesperson, Jonathan Allen, told The Globe and Mail that the delay comes from several connected issues spread across engineering, procurement and construction, according to World Nuclear News, and he pointed to inflation and geopolitical risk too. Which, frankly, is about what you’d expect two partners to say when they still have to finish building the thing together. OPG, for its part, says it’s working with GE Vernova Hitachi to close out the outstanding engineering and keep the project moving as quickly as it can.

Why does unfinished engineering slow down a concrete pour?

It helps to know what a small modular reactor is supposed to be. Basically, it’s a nuclear plant cut down to a fraction of the usual size, built from a standard design you can copy over and over, with big chunks made in factories instead of on site. Each BWRX-300 is rated at about 300 megawatts, while the four big CANDU reactors at the existing Darlington station are rated at 878 megawatts each, per the American Nuclear Society. OPG plans four of the small ones, for 1,200 megawatts in all.

That’s a pretty sensible pitch on paper. The catch is the first copy.

Concrete is about as permanent as construction gets. Every pipe, anchor and cable run that passes through a wall has to be in the right spot before it sets, so if a pump or a valve design is still moving around, the pour waits for it. And a supplier can’t fabricate a part to a drawing that isn’t final. As far as I can tell, that chain reaction is what OPG means when it talks about construction execution and supply chain performance. Slow and expensive, basically.

Foundation slab
1,050 tons
About 2.1 million pounds, set in April 2026.
Source: OPG
Reactor building shaft
115 ft
About 115 feet below ground, where the slab sits.
Source: World Nuclear News, converted from meters
One reactor
300 megawatts
Unit 1 of four planned, 1,200 megawatts in all.
Source: OPG
NO LONGER EXPECTED
Commercial operation target
October 2030
OPG says Unit 1 won’t make it. No new date yet.
Source: OPG, November 10, 2026
Unit 1 budget
C$7.7 billion
About US$5.4 billion. OPG no longer expects to finish within it.
Source: OPG; US dollar conversion by World Nuclear News

The site hasn’t stopped

Darlington is still a busy job site, though. During the third quarter, crews finished assembling the tunnel boring machine that’ll dig and line the tunnel for the plant’s condenser cooling water, and OPG expects tunneling to start before the end of 2026. They also completed the first pour for the turbine building, which is where the steam will spin the turbine that drives the generator.

Why does a reactor need a tunnel? The BWRX-300 is a boiling water reactor, so water boils in the core and the steam goes straight to the turbine. Once that steam has done its job, it has to be cooled back into water and sent around again, and that takes a lot of cold water. Darlington sits on the north shore of Lake Ontario, which is pretty convenient for that.

Butcher also said critical work is still happening on site every day. So OPG is building and finishing the design at the same time, which is arguably the hardest way to build anything.

How late is it, then?

OPG hasn’t put a number on it. The utility hasn’t given a new commercial operation date or a new budget, and as of November 16, I haven’t seen either one published. What OPG has said is that it’s running a full assessment of cost and schedule that should be substantially complete by mid-2027.

So what did that missed date actually mean? Commercial operation is the point where the unit is officially up and selling power to the grid as a working plant. That comes after fuel loading, testing and a stack of regulatory sign-offs, well after the reactor first starts up.

And October 2030 apparently wasn’t even the first date on the board. OPG’s own project page still lists an older planning goal of making the first unit commercially available by the end of 2029. A couple of you didn’t buy the original budget either, judging by the comments under our July piece.

Still, I’d argue the bigger question is what this does to units two through four. The whole modular argument rests on the later copies getting cheaper and faster because the engineering’s already done. If the first one is where that engineering gets finished, it’s safe to assume Unit 1 is where most of that bill lands. First-of-a-kind builds often go this way. It’s just more visible when the foundation is already sitting at the bottom of a shaft.

OPG calls Darlington the G7’s first small modular reactor, and the province still has four of them planned on the site. The tunnel boring machine is due to start digging before the end of 2026, and OPG expects its new cost and schedule assessment to be substantially complete by mid-2027.

THE LOTvia The Lot

Did we nail it or blow it?

Sign in with Google when you post
ROOKIE›DRIVER›ENTHUSIAST›EXPERT›LEGEND ★
THE LOTOwner community
Visit →
Luis Reyes

Luis Reyes

With more than 14 years covering the automotive industry, Luis Reyes is a seasoned voice in the field. A law graduate, he channels his curiosity and expertise into the detailed analysis of national and international regulations that shape the automotive world. At Autonocion.com, Luis combines his strong legal background with a deep passion for vehicles — especially those that have left a mark on automotive history. His experience writing for multiple brands across the industry has established him as a trusted authority. Luis is committed to sharing his expertise and enthusiasm with enthusiasts and industry professionals alike, with a firm belief in the continuous evolution and innovation driving the auto industry forward.
Contact: info@autonocion.com
New 3D film · Watch on YouTubeThe First Hour of a War Could Ground Every US Fighter. Except The X-BAT