- 2 MONTHS AGO · ENERGYA generator rotor spinning 3,000 times a minute inside a Finnish reactor failed, got replaced with the last spare in the building, and that one failed again seven months later, so the unit has run at 735 megawatts instead of 890 ever since, and the redesigned one is not due until late 2027
- 1 MONTH AGO · ENERGYAn 850-megawatt battery pushed 700 megawatts into the grid for two straight hours, pulled almost 850 back out of it, and the grid operator has now cleared it to run at full power, nearly a year after a transformer failure cut its grid contract in half
- 3 WEEKS AGO · ENERGYSeven 406-foot wind turbines stand bladeless six miles off the Irish coast after a jack-up barge climbed out of the sea on four legs and pulled 18 blades off them nine at a time, and their owner now wants the towers down too, warning the steel degrades faster every year it stands
- 2 WEEKS AGO · ENERGYA transformer feeding a 1,300-megawatt French reactor on the Luxembourg border caught fire as crews switched it back on at the end of a refueling outage, a water spray put it out before the fire trucks arrived, and this weekend only one of the plant’s four reactors is on the grid
- TODAY · THIS ARTICLEA 243-ton turbine assembly nearly 24 feet across was lowered back into a French hydro plant with only millimeters between its blades and a new ring set in concrete, and the rebuilt unit later climbed to 45 megawatts on its way back to the grid
Hydroelectric plants get a pretty easy ride in the energy debate. Water comes down a river, spins a turbine, and keeps your lights on. And as long as your lights are on, most people never think twice about the machinery inside.
Hydro plants keep that reputation right up until a turbine needs a rebuild. Then somebody has to take apart a machine that weighs hundreds of tons, fix it, and put it back exactly where it was.
EDF, France’s state-owned power company, has been doing that at Rhinau, a hydro plant on the Rhine in Alsace with Germany on the opposite bank. Rhinau’s Unit 1 spent 18 months out of service while its Kaplan turbine was rebuilt, and it’s been back on the grid since the spring.
I’m less interested in the 18 months than in how tight the fit was. EDF’s team has described the turbine’s runner block, a 243-ton assembly nearly 24 feet across, going back into its pit with only a few millimeters between the blade tips and the ring around them. That ring was brand new, too, set into the powerhouse after crews demolished the original.
So how do you get something that heavy into a hole that tight?
It’s gotta be done slowly, right? EDF hasn’t published a step-by-step account of the lift, so I can’t tell you exactly how its riggers pulled it off. But ANDRITZ, the Austrian company that handled the turbine work, has laid out the order of operations, and the logic is pretty clear: ring first, runner second, generator last.
So what’s a Kaplan turbine?
A Kaplan turbine is basically a ship’s propeller running in reverse. Instead of the blades pushing the water, the river pushes the blades, and the blades can twist to suit how much water is coming through.
That design makes a lot of sense at Rhinau, where the Rhine only drops about 43 feet through the plant. You don’t get much pressure out of a 43-foot drop, so you make up for it by moving an enormous amount of water, and that’s a big part of why the runner here is so wide. The new seven-blade runners going into Old Hickory Dam in Tennessee measure 264 inches across, while Rhinau’s comes in at about 285 inches.
The blades spin inside a ring-shaped liner called the discharge ring. It’s the fixed surface the blade tips sweep past, and any gap between the two lets water slip through without turning anything. Which means a sloppy fit costs you power pretty much every second the unit runs, for decades.
Replacing the ring meant digging into the powerhouse
Swapping a discharge ring is a lot more work than it sounds. The Rhinau ring is embedded in concrete, so it’s effectively cast into the powerhouse structure. Getting the old one out means breaking up the concrete around it. Putting the new one in means setting it to a tolerance the blades will have to live with for the next few decades. Neither EDF nor ANDRITZ has said publicly what shape the old ring was in when it came out. I’d guess six decades of river water and sediment had something to do with it, but that’s my guess, and neither company has stated it.
If you read our piece on the Mactaquac dam in New Brunswick, you’ve seen what happens when the concrete around a turbine starts moving: the machine stops fitting its own housing. I’m not suggesting Rhinau had anything like Mactaquac’s swelling concrete, and nobody has said it did. Still, it’s a pretty good reminder that on a hydro plant, the concrete is basically part of the machine.
The runner block went back in first
According to the contractor, the new ring went in first, wrapping up the demolition phase of the job. Months later, the 243-ton runner block was lowered back into the turbine pit, which ended the rehabilitation work on the turbine components themselves.
That’s the lift EDF’s team was talking about with the millimeter clearances. Frankly, it’s the step I’d least want to lead.
Then came the generator. Its rotor, which spins inside the generator’s windings to make electricity, weighs about 303 tons and measures nearly 34 feet across.
Don’t mix the two up. The runner block is the turbine end, down in the water, and the rotor sits up top in the generator. Put the two weights together, and you’ve got roughly 545 tons of machinery spinning every time Unit 1 runs.
Unit 1 had to earn its way back onto the grid
Once everything was back together, Unit 1 still had to pass a series of tests before EDF could count on it again. The turbine supplier lists three steps: a run with no load on the generator, a first synchronization with the grid, and a climb up to 45 megawatts.
Synchronizing basically means getting the generator spinning at exactly the right speed and timing to match the grid before the breaker closes. It’s a bit like matching speed before you merge onto a highway, except getting it wrong here can seriously damage the generator. Nobody wants that.
You shouldn’t read that 45-megawatt figure as a power upgrade, though. ANDRITZ lists the runner at 40 megawatts, and neither company has presented the test as an uprate, so I’m treating it as a load test.
Rhinau is one of eight hydro plants EDF runs on the Rhine, according to the company’s guide to its Rhine hydro plants, and it has four Kaplan units. EDF hasn’t said publicly whether the other three are in line for the same treatment, so I’m not going to guess.
ANDRITZ, in its commissioning update dated June 2, says Rhinau Unit 1 is the third of seven refurbished Rhine units where it has worked on the discharge ring, and the first where its job covered taking the whole unit apart and putting it back together.
A reactor built from 664 two-inch uranium cubes hung on wires in heavy water under a German castle was Heisenberg’s last shot at a chain reaction, and two of the surviving cubes now show it needed about twice the uranium and heavy water it held, more of both than Nazi Germany hadEnergy · 11 hours ago
A 66-foot-deep gravel pit in Finland just started taking in about 100 million gallons of tap water, and once a nine-acre lid goes on top, it’s meant to hold enough summer heat at up to 194°F to cover as much as nearly a quarter of the town’s yearly heat demandEnergy · 13 hours ago
A 375,000-pound turbine now spins inside a Tennessee dam in place of one that ran for more than 80 years, and a federal watchdog just found that 196 of the 240 welds on the ring guiding water out of it failed on a job where some welders weren’t qualifiedEnergy · 16 hours ago