Follow us on Google Get our news on Discover Follow

While scientists kept working in the buildings on either side, a row of ten isotope labs in Tennessee came down in two months, each one in the late afternoon, and the six hot cells, the gloveboxes and four 2,000-pound gas tanks inside left as part of nearly 3 million pounds of waste

While scientists kept working in the buildings on either side, a row of ten isotope labs in Tennessee came down in two months, each one in the late afternoon, and the six hot cells, the gloveboxes and four 2,000-pound gas tanks inside left as part of nearly 3 million pounds of waste

{{author_name}}

Luis Reyes

Nov 15, at 5:00pm ET

Back in September, we covered the first of ten old isotope labs coming down at Oak Ridge National Laboratory in Tennessee. At the time, the plan was to have the rest of them gone by the end of the year, which seemed fairly ambitious for buildings that used to make radioactive material.

Well, they’re all gone. United Cleanup Oak Ridge (UCOR), the cleanup contractor working for the Energy Department at the site, announced on November 2 that demolition of Isotope Row is complete. DOE’s Oak Ridge Office of Environmental Management followed with its own write-up on November 10, and both say the knocking-down part took two months.

So how do you tear down ten contaminated buildings in two months?

You spend six years getting them ready first. That’s how long the whole project ran, and almost all of it happened before anyone brought in an excavator.

Isotope Row was a cluster of ten facilities built from the late 1940s through the early 1960s. They turned out radioisotopes for medicine, industry, science and national defense, and they stopped operating in the early 1990s. The buildings didn’t go anywhere after that, though. They sat in ORNL’s central campus for decades, still full of mercury, asbestos, leftover radioactive isotopes, contaminated gloveboxes and hot cells, plus old process systems that were hazardous in their own right.

So what was actually inside?

The headline items are the six hot cells. If you’ve never seen one, a hot cell is basically a room with heavily shielded concrete walls, shielded windows and mechanical arms that reach through the wall. A worker stands outside, moves a handle, and the arm inside copies the motion, so nobody has to share a room with the stuff that’s giving off radiation. (We wrote about one of those arms breaking and then being used to fix the other one back in October.)

Then you have the gloveboxes, which are sealed boxes with gloves built into the side. You put your hands in the gloves and work on whatever’s inside without touching it or breathing it in. Isotope Row’s gloveboxes were contaminated, and they had to come out too.

UCOR’s list also includes four 2,000-pound krypton tanks. DOE just calls them tanks that held an inert gas, which is the same thing, only a little more vague (krypton is a noble gas, so it doesn’t really react with anything). Those tanks weren’t there anymore by the time the demolition started.

One of the toughest jobs, according to DOE, was the overhead off-gas and ventilation piping. Off-gas is basically the exhaust side of a lab like this, meaning the ducts and pipes that pulled air and fumes away from the radioactive work so they could be cleaned up. Some of Isotope Row’s piping was made with a concrete mix that contained asbestos, it had become highly contaminated, and it ran 10 to 15 feet above the floor. So workers were dealing with radioactive contamination and asbestos at the same time, over their heads. DOE says that took specialized controls and packaging to pull off. Frankly, that’s a pretty miserable-sounding way to spend a shift.

All told, the project pulled out nearly 3 million pounds of waste. That figure covers all six years of cleanup and demolition.

DOE says the cleanup started with cutting off the utilities and clearing out hazardous waste, asbestos and anything that could burn. Workers didn’t get to the dirtiest stuff, the old process equipment and the ventilation, until that was done. Each building had to reach what’s called cold-and-dark status, which is the cleanup world’s way of saying every utility is shut off. DOE’s Oak Ridge office, UCOR, UT-Battelle (the contractor that runs ORNL) and DOE’s Office of Science worked on that together.

The lab kept working the whole time

Isotope Row sat right in the middle of ORNL’s central campus, and the lab kept running around it. UCOR and DOE both say the heavy equipment did its work in the afternoons, so it’d get in the way of active research as little as possible.

Neither announcement says why afternoons work better than mornings, and I’m not going to start guessing about scheduling on a nuclear site. Still, if you’re a researcher working nearby, you’d presumably at least know when the noise is coming.

Building 3033 went last on purpose

Of the ten, only one building gets named in UCOR’s write-up. That’s Building 3033, and it went last because it had elevated levels of tritium along with other contaminants.

Tritium is a radioactive form of hydrogen. Since it behaves chemically like regular hydrogen, it can work its way into things like water and concrete, and that’s what makes it a pain to keep in one place.

So what happens if you knock 3033 down first? According to UCOR, you risk its contamination spreading into the debris from the surrounding buildings. That could’ve meant tougher disposal requirements, higher costs and a longer project. It’s a pretty sensible bit of planning. You don’t want one building’s worth of tritium turning nine buildings’ worth of rubble into the expensive kind of waste.

Most of the rubble stayed on site

Once the buildings were down, most of the rubble stayed on site for disposal, which saved the cost of shipping it somewhere else. UCOR posted a video update on October 20 saying the buildings were demolished and debris removal was underway, so the November announcements are really the wrap-up.

COMPLETE
Demolition
10 buildings / 2 months
All of Isotope Row, at the end of a six-year project.
Source: UCOR, DOE Office of Environmental Management
Waste removed
~3 million lb
Across the full six years of cleanup and demolition.
Source: UCOR, DOE Office of Environmental Management
Torn down
12,000+ sq ft
Of buildings in ORNL’s central campus.
Source: UCOR, DOE Office of Environmental Management
Work hours
375,000+
Completed safely, according to the contractor.
Source: UCOR

UCOR puts the total at more than 12,000 square feet of buildings torn down and more than 375,000 work hours completed safely. I’ll admit 12,000 square feet sounded small to me for ten buildings. Then again, almost all of the hard work on Isotope Row happened inside those walls, years before the first one came down.

There are a couple of things these announcements don’t cover. Neither DOE nor UCOR puts a price on the six-year project in its write-up, and DOE hasn’t said what will go where Isotope Row stood. It only says the cleared ground opens up space for future research in the middle of the campus. Federal Project Director Michael Griswold says the work “reduces risks today while opening new opportunities for the laboratory’s tomorrow.”

So that’s ten for ten. DOE’s Oak Ridge cleanup office marked the end of the six-year Isotope Row project on November 10, eight days after UCOR announced demolition was complete.

THE LOTvia The Lot

Agree or laugh out loud?

Sign in with Google when you post
ROOKIE›DRIVER›ENTHUSIAST›EXPERT›LEGEND ★
THE LOTOwner community
Visit →
Luis Reyes

Luis Reyes

With more than 14 years covering the automotive industry, Luis Reyes is a seasoned voice in the field. A law graduate, he channels his curiosity and expertise into the detailed analysis of national and international regulations that shape the automotive world. At Autonocion.com, Luis combines his strong legal background with a deep passion for vehicles — especially those that have left a mark on automotive history. His experience writing for multiple brands across the industry has established him as a trusted authority. Luis is committed to sharing his expertise and enthusiasm with enthusiasts and industry professionals alike, with a firm belief in the continuous evolution and innovation driving the auto industry forward.
Contact: info@autonocion.com
New 3D film · Watch on YouTubeThe First Hour of a War Could Ground Every US Fighter. Except The X-BAT