Follow us on Google Get our news on Discover Follow

A second 1,680-ton boring machine with a 28-foot cutterhead has started chewing through the rock under New Jersey beside its twin, each one dragging 500 feet of gear and lining its tube with 850 concrete rings, and both get swapped out for new machines before the Hudson

{{author_name}}

Luis Reyes

Nov 22, at 12:30pm ET

A second 1,680-ton boring machine with a 28-foot cutterhead has started chewing through the rock under New Jersey beside its twin, each one dragging 500 feet of gear and lining its tube with 850 concrete rings, and both get swapped out for new machines before the Hudson

Digging one tunnel is a big enough job. The crews under New Jersey’s Palisades are digging two, and they’re now doing both at once.

The Gateway Development Commission, the agency building the new rail tunnel between New Jersey and Manhattan, announced on November 18 that its second tunnel boring machine has started mining the southern tube. GDC’s chief of program delivery, Jim Starace, told the agency’s board the launch happened the week before. Its twin has been grinding through the northern tube since early October.

That means both tubes of the new tunnel are finally under construction. If you missed the first one, we covered the 1,680-ton machine’s first spin back in October. So I won’t rehash the launch. What’s new this time is that GDC has put a count on the concrete these two machines will set, and it’s a lot more than I expected.

Cutterhead
28 ft 8 in
Diameter of each machine’s spinning front end.
Weight
1,680+ tons
With roughly 500 feet of trailing gantries, per GDC.
Drive per machine
5,100 ft
North Bergen portal to the Hudson County Access Shaft.
Lining per machine
~850 rings
Built from more than 5,000 concrete segments.
ACTIVE
Northern tube so far
~400 ft
More than 60 rings in place, as of GDC’s November 18 update.

So why run two machines at once?

The new tunnel has two tubes, and each one will eventually carry a single track. You could, in theory, bore one tube and then haul the same machine back to the start for the other. That would basically double the schedule, so it’s no surprise the project has a matched pair working side by side.

We first looked at this pair back in July, when they were still being bolted together in North Bergen. Each machine has a cutterhead 28 feet 8 inches across, and it drags a string of trailing gantries roughly 500 feet long behind it. GDC says the whole setup weighs more than 1,680 tons. Those gantries are where everything else lives, from the conveyor that hauls broken rock out of the tunnel to the stack of lining pieces waiting to go in.

Frankly, running both at the same time is the sensible call. GDC expects this whole stretch to take about a year, and nobody wants to sit through that twice.

These machines build the tunnel as they go

Both are single shield machines, which GDC says are designed for hard, dry rock. A single shield is basically a big steel tube with a spinning cutter on the front. The cutter grinds the rock face into chips, and inside the tube, the crew lines the fresh hole with concrete before the machine pushes forward off the ring it just built.

That lining comes in rings. GDC says each machine will set nearly 850 of them, using more than 5,000 precast concrete segments. According to Construction Dive, a small crane inside the shield hoists each segment up and workers bolt the ring together. GDC doesn’t say how many segments make up a single ring. If you divide one figure by the other, though, you get roughly six.

The spacing works out neatly too. Nearly 850 rings over 5,100 feet comes to about one ring every 6 feet. Double the totals for both tubes and you’re looking at around 1,700 rings and more than 10,000 pieces of concrete, every one of them lifted into place inside a machine sitting under a cliff. That’s a pretty serious jigsaw puzzle for a stretch of tunnel that’s roughly a mile long.

The first machine is about 400 feet in

By the time GDC put out its November 18 release, the northern machine had bored about 400 feet and installed more than 60 lining rings. That’s less than a tenth of its 5,100-foot drive.

If you’re thinking 400 feet in about six weeks sounds slow, I wouldn’t read too much into it yet. GDC’s one-year estimate already includes scheduled maintenance pauses. Starace also told the board he expects production to keep climbing all the way to Weehawken. The southern machine, meanwhile, has barely started.

“The second one is really just beginning,” Starace told the board, according to Construction Dive.

So why swap machines before the river?

You’d think a machine that’s already chewed through a mile of rock could just keep going. Why can’t it?

Because the ground changes. The Palisades are solid, dry rock, but GDC says the river stretch has mixed ground conditions. That’s tunnel-speak for a face that can be part rock and part soft, wet soil at the same time. A machine built to grind hard rock in the dry isn’t designed to hold back loose, waterlogged ground, so the plan has always been to bring in a different pair for the trip under the Hudson.

The handoff happens at the Hudson County Access Shaft, on the border of Weehawken and Hoboken. Both Palisades machines finish their 5,100 feet there and get pulled out. Then two new machines built for the river take over and dig the rest of the way to Manhattan. GDC’s release doesn’t say much about the river machines beyond the ground they’re built for.

It’s arguably the weirdest bit of the plan if you picture one machine going end to end. But it’s pretty much the same logic you’d use in your own garage: you don’t cut tile with a wood blade. That shaft isn’t ready yet, either. Crews there are 50 to 60 feet down so far and have hit rock, according to Construction Dive.

The handoff is about a year away

Schiavone Lane Dragados JV is building this stretch, which also includes the access shaft, with the Port Authority of New York and New Jersey managing delivery alongside GDC. Starace told the board he expects the shaft to be done, and both machines to punch through into it, roughly a year from now. The river machines aren’t due to start digging until 2028.

Until then, GDC’s November 18 count stands at about 400 feet and more than 60 rings for the northern machine, and the southern one has nearly 850 rings still ahead of it.

THE LOTvia The Lot

Did we nail it or blow it?

Sign in with Google when you post
ROOKIE›DRIVER›ENTHUSIAST›EXPERT›LEGEND ★
THE LOTOwner community
Visit →
Luis Reyes

Luis Reyes

With more than 14 years covering the automotive industry, Luis Reyes is a seasoned voice in the field. A law graduate, he channels his curiosity and expertise into the detailed analysis of national and international regulations that shape the automotive world. At Autonocion.com, Luis combines his strong legal background with a deep passion for vehicles — especially those that have left a mark on automotive history. His experience writing for multiple brands across the industry has established him as a trusted authority. Luis is committed to sharing his expertise and enthusiasm with enthusiasts and industry professionals alike, with a firm belief in the continuous evolution and innovation driving the auto industry forward.
Contact: info@autonocion.com