Follow us on Google Get our news on Discover Follow

A 400-ton generator at a South Dakota dam was taken apart for the first time in 70 years, its 275-ton rotor lifted out by two cranes working as one, and the first new turbine runner has now rolled into the powerhouse to take each unit up to 52 megawatts

A 400-ton generator at a South Dakota dam was taken apart for the first time in 70 years, its 275-ton rotor lifted out by two cranes working as one, and the first new turbine runner has now rolled into the powerhouse to take each unit up to 52 megawatts

{{author_name}}

Luis Reyes

Nov 18, at 1:55pm ET

Nobody rips out a furnace that’s still heating the house. You wait for the weird noise, or for the repair guy to make that face, and then you start shopping.

The Army Corps of Engineers is taking pretty much the opposite approach at Fort Randall Dam, which holds back the Missouri near Pickstown, South Dakota. All eight of its hydroelectric generators are coming apart, and the Corps says none of them is broken.

So why bother?

Mike Schenkel, who manages maintenance and operations at the dam, gave the Yankton Press & Dakotan a pretty simple answer. Generators like these usually get a design life of around 40 years, and Fort Randall’s have been spinning since the mid-1950s without ever being disassembled. “We’re doing this just because it’s due,” he said. Nothing’s wrong with them right now. Honestly, I’d call 70 years out of a 40-year machine a win. Most of us can’t get a dishwasher past its warranty.

The job also just hit the first milestone you can actually watch. On September 23, the first of eight new turbine runners was moved from a temporary storage site into the powerhouse, and the Omaha District put a 64-second clip of it on DVIDS on October 15. As of November 18, the Corps hasn’t said the first rebuilt unit is generating again. We’ll get to that.

So what got delivered?

The runner is the big wheel at the base of each unit, and it’s what the river shoves against to make everything turn. Fort Randall’s are the Francis type: water rushes in from all sides, spins the wheel, then falls away underneath.

A tall vertical shaft connects that wheel to the generator’s rotor, which is basically an enormous electromagnet. The rotor turns inside the stator, a fixed ring of copper coils, and that’s where your electricity comes from.

Here’s the catch. Everything’s stacked, with the runner on the bottom, so you can’t swap the wheel without first clearing out whatever’s above it. And the biggest piece up there is the rotor.

The rotor’s too heavy for either crane

Schenkel says a full unit, generator through turbine, comes to roughly 400 tons and more than 40 feet from top to bottom. The Mitchell Republic put the rotor by itself at 275 tons.

The powerhouse’s two overhead cranes are rated for 155 tons apiece, so neither can do that lift solo. Working in tandem, the pair can handle 310 tons, which leaves a 35-ton cushion. That sounds like plenty until you picture what’s hanging off the hooks. Personally, I’d want the operator to have skipped the second coffee that morning.

Both cranes were originally rated at 150 tons, and the Corps had them rebuilt and re-rated, along with their 280-ton lifting beam, well ahead of this job. You don’t do that on a whim, so it’s safe to assume this lift sat on someone’s whiteboard for years. Schenkel told the Press & Dakotan the planning started roughly a decade before the work.

What does the Corps get for the money?

The rehab costs about $150 million. Each rebuilt unit is rated for 52 megawatts, up from about 42 in Schenkel’s Press & Dakotan interview or 43 in the Mitchell Republic’s. The Corps calls Fort Randall a 320-megawatt plant today and expects roughly 400 when the last unit’s done.

Eight units at 52 apiece actually comes to 416, so I’d treat 400 as rounding rather than a guarantee. You’ll also see 50 megawatts in some older coverage, including the Corps’ own contract-signing story, but both recent print interviews say 52.

Turbine efficiency climbs as well, to about 92% from roughly 89%. Frankly, that’s my favorite part of the project. The river isn’t getting any bigger, so getting more out of every gallon that already flows through the turbines is about as cheap as extra power gets.

The contractor is Voith Hydro, which makes the runners at its York, Pennsylvania, shop. According to Schenkel, the turbine design took a year or so, and manufacturing took another. Besides the runners, the contract covers work on the generators’ stators.

The plant doesn’t go dark while all this happens. Fort Randall is a peaking plant, which means it’s there to cover the hours when demand is highest instead of humming along all day. Schenkel says it usually runs hard through the evening rush, then sits idle from roughly midnight until 6 a.m.

That’s also why the schedule is so cautious. The contractor has to finish one unit before it’s allowed to work on two at once, and even then the outages overlap, with one unit coming apart while the other is going back together. The rest keep making power.

Unit and rotor
400 tons / 275 tons
A complete unit, more than 40 feet tall, and the generator rotor that has to come out first.
Source: Mike Schenkel, USACE, to Yankton Press & Dakotan and Mitchell Republic
Powerhouse cranes
2 × 155 tons
310 tons working together, 35 tons over the rotor. Both were originally 150-ton cranes.
Source: Mitchell Republic; USACE crane re-rate solicitation
TARGET
Output
42–43 → 52 MW
Per unit. The whole plant goes from 320 MW to about 400 MW.
8 × 52 = 416, so 400 is a round number, not a promise. Source: Schenkel to Press & Dakotan and Mitchell Republic
First new runner
Sep. 23, 2026
The first of eight new runners moves from temporary storage into the powerhouse.
Source: USACE Omaha District video, DVIDS

So is Unit 6 back online yet?

Unit 6 went first. Work started last summer, and a Corps photo the Press & Dakotan ran shows its first big section being hoisted clear on August 27 of last year. By February, its shaft and original runner were both lying on the floor of the powerhouse, and Corps captions from that February tour say the shaft is being reconditioned to go back in with new stator casings, a new runner and the refurbished rotor.

Every forecast I’ve seen points at right about now. The Press & Dakotan reported last fall that the first outage would run into fall 2026, the Mitchell Republic reported the first new generator was due online late this year, and a rural electric co-op’s June newsletter said the Corps expected it offline until November.

So is it back? As of November 18, I haven’t found an announcement from the Corps, the Omaha District or the local press that Unit 6 is generating again. That doesn’t mean it’s late. November isn’t over, and the Corps doesn’t exactly live-tweet its powerhouse. I just can’t tell you it’s done.

The September video also never says which unit gets the new runner. Nobody’s reported any other unit as open, so Unit 6 is my guess, but it’s a guess. And there’s still no published diameter or weight for the new runner, which feels like a strange detail to skip when it’s the star of the video.

How long will all eight take?

The Mitchell Republic described each unit as an 18-month build-and-test job, and the finish date shifts depending on who you ask. When Voith won the work, the estimate was December 2031. Local coverage has said summer 2031. The Corps’ February captions say the contract runs to September 2032. I’d lean on that one. It’s the newest, and it’s the Corps’ own paperwork.

For comparison, the New York Power Authority spent 33 months on the first of Niagara’s 13 turbines, so a year and a half per unit would be a pretty brisk clip. And Fort Randall isn’t the Corps’ only patient. It’s been swapping in new Kaplan runners for the 1950s originals at Old Hickory Dam in Tennessee, and on October 20 it lifted a generator rotor out of McNary Dam‘s Unit 14 on the Columbia.

Seven more runners still have to make the same trip from storage, and the first one has been inside Fort Randall’s powerhouse since September 23.

THE LOTvia The Lot
3 comments

Did we nail it or blow it?

Sign in with Google when you post
ROOKIE›DRIVER›ENTHUSIAST›EXPERT›LEGEND ★
@hollycaines ROOKIE2 weeks ago
Id like to know who got the Contract to dispose of the old unit.. How much salvageable Copper and recyclable material there is at today's prices..and What is done with the Cooling oils that have PcB's in it when they Crack it open- How much it cost to properly-enviormentally dispose of Carcinogenic material safely.. And What the bid was to aquire the old unit for Salvage and Who got it?
0
@susancrawford ROOKIE2 weeks ago
Very interesting since, I retired working in coal fired power plants. Thanks!
0
gregmccann ROOKIE2 weeks ago
What do they do with the old runners? Scrap them, refurbish them?
0
THE LOTOwner community
Visit →
Luis Reyes

Luis Reyes

With more than 14 years covering the automotive industry, Luis Reyes is a seasoned voice in the field. A law graduate, he channels his curiosity and expertise into the detailed analysis of national and international regulations that shape the automotive world. At Autonocion.com, Luis combines his strong legal background with a deep passion for vehicles — especially those that have left a mark on automotive history. His experience writing for multiple brands across the industry has established him as a trusted authority. Luis is committed to sharing his expertise and enthusiasm with enthusiasts and industry professionals alike, with a firm belief in the continuous evolution and innovation driving the auto industry forward.
Contact: info@autonocion.com