Follow us on Google Get our news on Discover Follow

A 79-foot steam generator weighing about 694 tons, nearly 20 feet across, was hoisted into a Guangdong reactor building on Wednesday, the first of two for a 1,250-megawatt unit whose steel vessel went in this summer, a lift its builder said was kept stable and precisely controlled

A 79-foot steam generator weighing about 694 tons, nearly 20 feet across, was hoisted into a Guangdong reactor building on Wednesday, the first of two for a 1,250-megawatt unit whose steel vessel went in this summer, a lift its builder said was kept stable and precisely controlled

{{author_name}}

Luis Reyes

Nov 13, at 11:00am ET

Ask most people to picture a nuclear power plant and they’ll probably describe the cooling towers. Some will mention the reactor. Fair enough. But a reactor doesn’t make electricity on its own. It makes heat, and something has to turn that heat into steam before a turbine can do anything useful with it.

That something is called a steam generator, and on Wednesday one of them went into the reactor building of Lufeng unit 1, a plant under construction in China’s Guangdong province. It’s about 79 feet long and nearly 20 feet across. It weighs about 694 tons, too, and it’s only the first of two that unit needs.

The builder is China Nuclear Industry 23 Construction Company, or CNI23, a subsidiary of state-owned China National Nuclear Corporation. CNI23 is putting the unit up under contract to China General Nuclear (CGN), and it announced the lift itself. World Nuclear News picked the story up on Thursday, with CNI23’s summary of the job: “The entire process was safe, stable, and precisely controlled.”

Which is pretty much the only acceptable way to describe moving 694 tons of anything around inside a reactor building.

So what is a steam generator?

Lufeng 1 uses a design called the CAP1000, China’s version of the Westinghouse AP1000. If that name rings a bell, it’s because the AP1000 is the design running at Plant Vogtle in Georgia. Both are pressurized water reactors, and the basic idea is easier to follow than you’d think.

Water flows through the reactor core and picks up heat, but it’s kept under so much pressure that it can’t boil. That hot water then gets pumped through a big bundle of thin metal tubes inside the steam generator. On the outside of those tubes sits a separate supply of water at lower pressure, and that water does boil. The steam heads off to spin the turbine.

That means the water that touches the fuel never gets anywhere near the turbine, which is kind of the point. Basically, a steam generator is a giant heat exchanger that keeps two batches of water apart while passing heat from one to the other.

The CAP1000 uses two of them per reactor, each one serving its own coolant loop. And if you’ve followed our coverage of French reactors, you’ll know they do things a little differently. The Paluel plant’s unit 3 is getting four replacement steam generators at 474 tons each, while a reactor at Cruas-Meysse is getting three that weigh about 365 tons apiece.

So why is Lufeng’s so much heavier?

It comes down, at least partly, to the number of loops. With only two steam generators sharing the heat from a 1,250-megawatt reactor, each one has to handle a bigger slice of it than its French cousins do. And as you’d expect, a bigger slice means a bigger machine.

THIS WEEK
Lufeng unit 1 · Guangdong
~694 tons
Each steam generator. Two per reactor. About 79 feet long, nearly 20 feet across. First one hoisted in on Wednesday.
Paluel unit 3 · France
474 tons
Each replacement steam generator. Four per reactor. In storage at the plant until the reactor’s overhaul.
Cruas-Meysse · France
~365 tons
Each replacement steam generator. Three per reactor. In storage at the plant until the reactor’s overhaul.

Flipping it was arguably harder than lifting it

A Chinese-language write-up on CINIE, a nuclear construction news site, fills in some detail WNN’s piece doesn’t. It matches WNN on the weight, then describes the job as a stack of headaches: the sheer tonnage, a tricky flip on site, and very little room to maneuver inside the nuclear island.

Steam generators usually travel lying on their side, so “flipping” most likely means tilting this one up to vertical before it went down into the containment. Doing that with 694 tons on the hook isn’t something you’d want to improvise.

And they didn’t. According to CINIE, the team went through several rounds of plan reviews, tabletop rehearsals, digital modeling and process simulation before the lift. It also mapped out stress risk points, tweaked the lifting path and had custom lifting fixtures made. During the lift, 3D collision checks and guide devices helped steer the steam generator through the flip, into the containment cavity and into position. CINIE says the final placement landed within the design tolerance.

That’s a lot of rehearsal for one lift.

Neither write-up says how long it took or names the crane that did it. I’d have liked to see both, frankly, since the crane was arguably the hardest-working machine on that site this week.

Lufeng is a six-reactor site

If Lufeng sounds familiar, that’s because we were at Lufeng back in July, when a steel structural module of about 2.1 million pounds was lowered into the reactor building of unit 2 next door. That was a different piece of hardware on a different unit, but it’s the same reactor design.

According to WNN, Lufeng is laid out for six units in total. Units 1 through 4 are CAP1000s. Units 1 and 2 already have State Council approval, while 3 and 4 haven’t gotten theirs yet. Units 5 and 6 use a different Chinese design called the Hualong One, and they’re further along, with unit 5 expected to enter service in 2027 and unit 6 in 2028.

Unit 1 itself got its first safety-related concrete in February of last year. Its reactor pressure vessel, the thick steel pot that holds the fuel, went in this July, and now the first steam generator is in place about four months later. From where I’m sitting, that’s a pretty brisk rhythm for a reactor build.

It’s also a bit of a contrast with how the AP1000 fared in the US, where Georgia eventually got its Vogtle reactors running but South Carolina left a half-built plant behind. China seems pretty happy to keep building the design in batches.

There’s still a lot of welding to do

The second steam generator hasn’t gone in yet. After that, CINIE says the next big job is assembling and welding the main coolant piping, the heavy pipes that tie the reactor vessel and the steam generators together into one sealed circuit. The project team also has more large nuclear island equipment to install, and it’s pushing to hit its construction targets for the year before the fourth quarter wraps up.

So if you were hoping to see Lufeng 1 send power anywhere soon, don’t hold your breath. WNN says units 1 and 2 are both expected to enter service in 2030, and as of Wednesday, unit 1 has the first of its two steam generators in place.

THE LOTvia The Lot

Agree or laugh out loud?

Sign in with Google when you post
ROOKIE›DRIVER›ENTHUSIAST›EXPERT›LEGEND ★
THE LOTOwner community
Visit →
Luis Reyes

Luis Reyes

With more than 14 years covering the automotive industry, Luis Reyes is a seasoned voice in the field. A law graduate, he channels his curiosity and expertise into the detailed analysis of national and international regulations that shape the automotive world. At Autonocion.com, Luis combines his strong legal background with a deep passion for vehicles — especially those that have left a mark on automotive history. His experience writing for multiple brands across the industry has established him as a trusted authority. Luis is committed to sharing his expertise and enthusiasm with enthusiasts and industry professionals alike, with a firm belief in the continuous evolution and innovation driving the auto industry forward.
Contact: info@autonocion.com