- 3 MONTHS AGO · ENERGYA crane lowered eight 12-foot fuel bundles into a reactor on the Lake Michigan shore on Sunday, 196 short of a full core, four years after the vessel was emptied for scrapping, and some of the bundles going back in are the ones that were in it when it shut down
- 2 MONTHS AGO · ENERGYA 12-foot bundle of 216 fuel rods tilted over inside the first American reactor being pulled back from decommissioning, after the loading machine had set it in the core and let go, and engineers are now designing tools just to lift that one bundle back out
- 1 MONTH AGO · ENERGYA 12-foot bundle of 216 fuel rods has held up the first American reactor ever brought back from retirement for five weeks by leaning over in its core, a one-off tool is being built from scratch just to lift it back out, and the restart due early next year no longer has a date
- 1 MONTH AGO · ENERGYA 19,000-megawatt air-cooled reactor in Idaho fires 80-millisecond pulses into used fuel rods to make them fail on purpose, and 192 neutron detectors watch the uranium move inside the sealed steel capsule through a 2.75-inch slot in the graphite, 1,000 times a second
- TODAY · THIS ARTICLEA 12-foot bundle of 216 fuel rods leaning 30 degrees inside the first American reactor brought back from retirement will be laid flat in a 49,000-pound steel canister and hoisted out of the water by the crane that lifts the reactor head, a move no plant has made before
A nuclear fuel bundle has two jobs while it’s being moved: stand up straight, and stay underwater. For about seven weeks now, one of the 204 bundles at Palisades has only been managing the second one.
However, that’s about to change. On October 13, the Nuclear Regulatory Commission signed off on a plan to lift the leaning bundle out of the first American reactor ever brought back from retirement, and the plan is quite stranger than I expected. Guess those jobs were not all that simple after all.
The bundle doesn’t go out the way fuel normally leaves a reactor. It goes into a 49,000-pound steel canister, gets hoisted out of the water by the big crane that normally handles the reactor head, and rides across the containment building through a hatch built for equipment, not fuel.
We’ve been on this story since the day the first bundles went back in. If you missed the earlier rounds, here’s where things stood two weeks ago. The short version: Holtec started loading fuel into the reactor in Covert, Michigan, on August 30, got eight of the 204 assemblies in, and one of them tilted over after the loading machine set it down and let go. Everything fuel-related stopped right there.
Now we know how it gets out, and when.
So how do you pick up a fuel bundle that won’t stand up?
Not with the machine that put it there, apparently. Holtec told the NRC that visual inspections showed damage to the top of the assembly, the part the loading machine’s grapple is supposed to lock onto. The bundle, which the paperwork calls DD41, is leaning at roughly 30 degrees, with its bottom still seated in its slot and its top resting against the shroud that surrounds the core. You can’t grab the top, and you can’t just drag it, because the 216 rods inside are the whole point of keeping it intact.
So Holtec’s engineers built something new. The plan the NRC approved uses the containment polar crane, the one that lifts the reactor vessel head during a normal outage, with a custom-made fuel movement device hanging off it on slings and chain falls. That device grips the bundle by its structural guide bars, which are the bits of the frame that hold the rods in place, and lifts it free. At all times, there must be at least 10 feet of water over the fuel.
Then it gets laid down. Horizontally. Into a steel canister sitting on the floor of the flooded reactor cavity. Once the lid is on and the bundle is confirmed to be sitting right, the crane lifts the loaded canister, all 49,000 pounds of it, clear of the water; the crew drains it, and it travels across containment on the crane’s existing rails to the equipment hatch. From there, a trolley carries it into the spent fuel pool building, and a second crane picks it up, stands it upright, and lowers it into the cask pit at the pool’s edge.
If that sounds like a lot of handling for one bundle, it is. The NRC’s own safety evaluation calls it a first-of-a-kind fuel movement.
The normal route is a tube, and this bundle can’t use it
This is the bit I had to look up, so let me save you the same trouble. In a pressurized water reactor like Palisades, fuel doesn’t get carried through the plant. It gets passed through a wall. The refueling machine picks a bundle up from the core, sets it in a carriage, and the carriage tips the bundle onto its side, where it slides through a transfer tube from the containment building into the spent fuel pool next door, underwater the entire way. Then it’s tipped back upright and parked in a rack.
Which means the plant’s entire accident analysis for fuel handling assumes the fuel is at least 23 feet underwater if anything goes wrong. Water does two things there: it shields the workers, and if a rod ever cracks, it holds onto a good chunk of what comes out.
DD41 can’t go through the tube because the machine that feeds the tube can’t grab it. So Holtec’s plan removes the bundle from the water, which is why it required an amendment to the plant’s license rather than a procedural change. The NRC’s reviewers had to rerun the accident math again with no water to credit for part of the trip, and they did so on the assumption that the canister is dropped with the equipment hatch wide open and every rod in the bundle fails.
Their answer was that doses at the site boundary and in the control room stay under the federal limits. The agency also ran its own shielding calculations for the canister and said the radiation levels during the dry stretch should be similar to those on a normal outage job.
Does that mean there’s nothing to it? Not at all.
This is a used bundle, from the plant’s last runs before the 2022 shutdown, and the NRC’s evaluation treats it as irradiated fuel with about four years of decay behind it. The canister isn’t sealed either, so the plan includes a water chemistry sample right after the lid goes on, to confirm nothing cracked while the bundle was being straightened, and radiation protection staff watching the air monitors through the lift. The NRC’s letter notes those monitors may alarm as the canister breaks the surface, and that someone has to be standing there deciding whether that’s the water or the fuel.
Straightening a bent bundle inside a box
One of you called this in the comments on our last piece. The bundle bent. The NRC’s review says the upper tie plate is bowed, and the fuel vendor’s evaluation predicts up to 3 inches of plastic deformation, meaning the bundle has taken a set and won’t spring back on its own.
That raised an obvious question at the NRC, and I’d have asked it too. The canister drawings didn’t seem to leave room for a bundle that’s bowed, so what happens when you put the lid on a 12-foot assembly that isn’t straight?
Holtec’s answer, backed by the vendor, is that the lid pushes it straight, and that the frame absorbs the force rather than the rods. The grid straps and guide bars take the strain, which is what they’re designed for, and the rods stay inside the envelope of the lid. The NRC didn’t just take that on faith. It got Holtec to add a stop-work rule: once the bundle is sitting on its pedestals inside the canister, cameras check the gaps, and if any gap between the bundle and the pedestals is bigger than 2 inches, work stops and the site re-evaluates. There’s a marked alignment tool for reading that 2 inches on camera. The largest gaps, if any, are expected at the top end, where the damage occurs.
Two inches is the whole margin. I find that pretty reassuring, to be honest, because it’s a number someone can see on a screen rather than a judgment call made at the lip of a reactor cavity.
Another reader argued the special tooling was only needed because a fuel assembly is heavy. I get the logic, but that isn’t what the filings say. The loading machine lifts these bundles for a living. The problem is the damaged top, which the grapple can’t connect to, and the lean, which puts the bundle somewhere the grapple can’t reach. The weight is why the NRC classified the loaded canister as a heavy load and demanded a drop analysis, which Holtec ran three ways: flat, top end first, and bottom end first, and the canister held together in all three.
Holtec asked for an emergency, and the NRC said exigent
This part of the paperwork is the one I’d have skipped if I’d been reading fast, and I’m glad I didn’t. Holtec filed on September 30 and asked for the amendment to be processed as an emergency, which would have meant no public notice and no comment period at all. The NRC said no to that. It processed the request as “exigent” instead, a notch down, which still skips the usual 30-day comment window but requires the agency to tell the public somehow. In this case, that meant notices in the Grand Rapids Press, the Kalamazoo Gazette and the Herald Palladium, and a three-day window to comment.
Twenty people wrote in. The NRC says most of the comments were out of scope, which in regulator-speak means they were about whether Palisades should restart at all rather than about this specific lift. One commenter, though, pushed hard on bowing, and the NRC’s answer is the 2-inch rule above. So the comment period did something.
The NRC also reviewed the pool-side crane that stands the canister upright, and confirmed it’s still configured as single-failure-proof from the plant’s last dry cask loading campaign. Basically, that’s a crane built so one broken part can’t drop the load. The path the canister takes runs over a pit where spent fuel is stored, so Holtec had to show the agency that an existing analysis of a cask drop onto 73 stored assemblies bounds anything this smaller canister could do. It does, the NRC agreed, because the canister isn’t big enough to hit 73 of anything.
Holtec said in a statement that the approach “was supported by engineering evaluations addressing structural integrity, fuel handling, thermal conditions, and radiation protection.” The NRC told The National its specialists and resident inspectors will keep watching the removal.
What this does to the restart
Nothing official. Holtec still hasn’t put a date on it, and Patrick O’Brien, the company’s director of government affairs and communications, gave The National the line the company has used for months: Palisades “will return to service when all required work is complete and all federal requirements and industry standards are met.” A source close to Holtec told The National the company hopes to be back online by March 2027. I’d treat that as a hope. March is also the month the plant owes power to its two co-op customers, making it as much a deadline as a forecast.
The same week the amendment landed, the NRC sent Holtec a separate letter saying its inspection found what it called a chilled work environment in two departments at the plant, supply chain and quality assurance, where employees may be hesitant to raise safety concerns. The agency said it found no violations or significant plant safety issues, and Holtec said it’s taking action. I mention it because it’s on the record, landed the same week, and isn’t about this lift.
The lift itself is the thing to watch. Once DD41 is in the pool, fuel loading can restart, 196 bundles still have to go in, the vessel head has to go back on, and the plant can finally move down the ladder toward cold shutdown and, eventually, power. That’s weeks of work before anyone pulls a control rod.
Amendment No. 283 to Palisades’ operating license was issued on October 13, 2026, and has to be implemented within 10 days of that date.
A 1.88-inch setup error on a Washington campus reactor sent a pulse rod out of its cylinder at 9.13 inches instead of 7.25, because the operator used the numbers for the wrong control rod, and the fuel peaked at about 1,598°F, some 72 degrees over the pulse limit but under the safety limitEnergy · 8 hours ago
A 170-foot concrete tower in a California reservoir has had 40 feet cut off its top, ring by concrete ring from a crane on a floating barge, because the dam beside it was built 33 feet lower than planned and left the tower that is the lake’s only safe drain too tall for an earthquakeEnergy · 11 hours ago
A 1,207-megawatt reactor in Washington state was shut down by hand at 2:49 in the morning after both pumps pushing water through its core tripped five minutes apart, all because one blown fuse knocked out the chillers cooling their drives, and it stayed off the grid for over five daysEnergy · 13 hours ago