Follow us on Google Get our news on Discover Follow

A 1.8-megawatt wind turbine on a 257-foot tower, with 132-foot blades reaching nearly 400 feet, is one of four to be lowered by crane this fall at Ohio’s first commercial wind farm after more than 20 years, and crews will then excavate foundations about 33 feet deep, due by mid-December

A 1.8-megawatt wind turbine on a 257-foot tower, with 132-foot blades reaching nearly 400 feet, is one of four to be lowered by crane this fall at Ohio’s first commercial wind farm after more than 20 years, and crews will then excavate foundations about 33 feet deep, due by mid-December

{{author_name}}

Luis Reyes

Nov 16, at 5:00pm ET

Most of the wind turbines that make the news are either brand new or broken. A developer wants to put up a bigger one, or, like the turbine at a Missouri wind farm back in August, a tower ends up bent over in a field. The four turbines outside Bowling Green, Ohio, don’t fit either category. They’re just old, and they’re due to come down by crane, on a schedule, one at a time.

The city calls the site Ohio’s first commercial wind farm, and its own project page also describes it as the state’s first utility-scale wind project. The turbines started making electricity in 2003, kept at it for more than 20 years and were officially retired in 2025. Now Bowling Green is paying to get rid of them.

So what does it actually take to remove a wind turbine this size?

There’s a lot of turbine to take down

Each of the four is a 1.8-megawatt machine on a 257-foot tower, according to a 2016 annual report from American Municipal Power, the group that developed the wind farm as a joint venture of Ohio towns. The blades reach 132 feet out from the turbine housing. When one of them swings straight up, the whole thing stands nearly 400 feet tall.

Those are AMP’s own figures from 2016, not something anyone’s re-measured since. Then again, steel towers don’t tend to shrink.

Tower
257 ft
Height of each of the four towers (AMP, 2016 annual report).
Blades
132 ft
How far each blade extends from the turbine housing (AMP).
Blade tip at the top
Nearly 400 ft
Total height with a blade pointing straight up (AMP).
Foundation
About 33 ft
Depth below ground, to be dug out without blasting (City of Bowling Green).

For a sense of scale, 132-foot blades look pretty modest by today’s standards. A developer in Australia now wants a new road built just so its 213-foot blades can get around a roundabout.

The city’s plan is to take the four turbines down one at a time over the fall. Big cranes handle the lifting. The blades and nacelles get lowered to the ground that way, and the towers come apart in sections. If you’ve never had to think about a nacelle, it’s basically the box at the top of the tower that holds the gearbox and the generator, which is what turns spinning blades into electricity.

Then there’s the stuff you can’t see. Each turbine sits on a foundation that goes approximately 33 feet into the ground, and those get dug out too.

That might sound like overkill. But think about what a foundation’s job is here. A tall tower with three long blades catches a lot of wind, and all that sideways push is constantly trying to tip it over. The foundation is the anchor that stops it, so it has to be big, heavy and deep.

Bowling Green says the excavation will happen without blasting, and each site gets backfilled and restored afterward. The city doesn’t say why explosives are off the table, though I’d guess a working county landfill right next door has something to do with it. The landfill stays open to the public through all of this, and the city’s warned residents they’ll probably notice more activity and cranes.

Has anything come down yet?

The prep work started in August. According to BG Independent News, which covered the start of the job in late August, that first stage meant pulling out underground electrical infrastructure, with the turbines themselves to follow.

The city’s project page still talks about the crane work in the future tense. City council heard updates on Sept. 8 and Oct. 19, though neither said a turbine was already down. So I can’t tell you which of the four, if any, has already been lowered. What we do know is the deadline, which I’ll get to.

Why not just swap in new turbines?

You’d think the obvious move would be to put newer turbines on the same spots. Bowling Green did look at that. Back in 2020, replacing each machine with a newer model was estimated at $8.8 million apiece, BG Independent reported.

The old ones weren’t cheap to keep alive, either. In 2020, the same outlet reported that a couple of gearboxes had already failed, at up to $500,000 each to replace. Replacement parts got hard to find, which isn’t too surprising when the city has said the turbines’ model, the Vestas V80, is obsolete. In 2021, one turbine was retired early because of repair costs. That cut the wind farm’s output from 7.2 megawatts, enough for about 2,500 residential customers, to 5.4 megawatts.

Even if the money had worked out, the site’s off the table. The city says the land won’t host renewable generation again, because the county needs it for future landfill space and Plain Township’s zoning rules get in the way.

It’s a bit of a shame, frankly. Still, BG Independent puts the turbines’ expected working life at roughly 20 years, and these made it past that, which is a pretty respectable run.

Nothing’s going into the landfill next door

I’ll admit I like how the city’s handling the leftovers. Bowling Green says none of the material will end up in the landfill. The plan is to recycle the metal, the wiring and even the foundation concrete, capture oil and other fluids where it can, and check whether the major components are worth selling or reusing.

That’s arguably a better outcome than in Casper, Wyoming, where the city landfill buried a whole lot of old turbine blades before it stopped taking them.

So who’s paying for it?

The demolition costs $1.77 million, according to BG Independent. Bowling Green owns 51% of the project, so it’s covering about half, and the nine other communities that share in the wind farm split the rest. The city’s been saving for its share through utility rates, which is pretty sensible planning for a machine you know is going to wear out.

$1.77 million to remove all four sounds like a lot. It’s arguably a bargain next to the $8.8 million that a single replacement was expected to cost in 2020.

Brian O’Connell, the city’s director of infrastructure and public utilities, didn’t pretend to be thrilled about it. “It’s sad to see them coming down,” he told BG Independent.

I get it. You don’t look at something that big on the horizon for two decades without getting a little attached.

Bowling Green isn’t giving up on renewables, though. The city’s renewable energy page says it’s working on a new solar project somewhere else to make up for the lost wind power, and BG Independent reports two possible sites near I-75. If the weather cooperates, Bowling Green expects the whole removal job, foundations included, to be finished by mid-December.

Credit: City of Bowling Green

THE LOTvia The Lot

Did we nail it or blow it?

Sign in with Google when you post
ROOKIE›DRIVER›ENTHUSIAST›EXPERT›LEGEND ★
THE LOTOwner community
Visit →
Luis Reyes

Luis Reyes

With more than 14 years covering the automotive industry, Luis Reyes is a seasoned voice in the field. A law graduate, he channels his curiosity and expertise into the detailed analysis of national and international regulations that shape the automotive world. At Autonocion.com, Luis combines his strong legal background with a deep passion for vehicles — especially those that have left a mark on automotive history. His experience writing for multiple brands across the industry has established him as a trusted authority. Luis is committed to sharing his expertise and enthusiasm with enthusiasts and industry professionals alike, with a firm belief in the continuous evolution and innovation driving the auto industry forward.
Contact: info@autonocion.com
New 3D film · Watch on YouTubeThe First Hour of a War Could Ground Every US Fighter. Except The X-BAT