A 97,000-ton nuclear aircraft carrier has now spent more than 2,000 days at the Virginia shipyard that built her, getting a new mast and work on over 600 tanks, and Navy documents point to one more year of it, with her sister ship already there for a five-year overhaul

A 97,000-ton nuclear aircraft carrier has now spent more than 2,000 days at the Virginia shipyard that built her, getting a new mast and work on over 600 tanks, and Navy documents point to one more year of it, with her sister ship already there for a five-year overhaul

{{author_name}}

Chema Bonilla Díaz

Nov 4, at 5:00pm ET

Anyone who’s ever waited on a contractor knows what “shortly” means. It could be tomorrow, or it could be after you’ve spent another Christmas without a kitchen.

So I got pretty curious when Stars and Stripes reported on October 1 that the USS John C. Stennis, a nuclear aircraft carrier that’s been in a Virginia shipyard since 2021, “is scheduled to depart shortly.” Almost five weeks later, I can’t find any announcement that she’s left, started sea trials, or been handed back to the fleet.

Then there’s the other date floating around. Navy budget documents, as reported by Janes, have the work wrapping up in November 2027. That’s a year from now.

The Navy’s fact file lists Nimitz-class carriers like the Stennis at 1,092 feet long and about 97,000 tons fully loaded. This one left Norfolk for the yard on May 6, 2021, which puts her at 2,008 days and counting as of today. She’s at Newport News Shipbuilding, the same place that built her.

So what’s she doing in there?

The job is called a Refueling and Complex Overhaul, or RCOH. A nuclear carrier is built to last about 50 years, and around the halfway mark it goes back to the shop to get fresh fuel in its two reactors and have pretty much everything else on board torn into.

We went through how the refueling side works when her sister ship, the Truman, showed up at the same yard, so I won’t repeat it here.

The Stennis work list is a long one. According to the Navy, she’s getting a new mast for her defense and communications gear, updated shafts, refurbished propellers and modernized equipment for launching and recovering aircraft. Then you’ve got more than 600 tanks, plus thousands of pumps, pipes and valves. She came out of dry dock on April 8, 2024, after the yard let in over 100 million gallons of water, and she’s been at an outfitting berth since.

The Navy’s estimate is north of 25 million man-hours. I ran the math on that, and one person on a 40-hour week would need about 12,000 years. Bring a lunch.

A single damaged generator caused a lot of this

These overhauls usually take about four years, according to Stars and Stripes. The Stennis was first due out in August 2025. Fiscal 2025 budget documents moved that to October 2026, a slip of almost 14 months, USNI News reported.

Most of that slip traces back to one machine. The ship has eight steam turbine generators, and they’re basically its power plant, turning reactor heat into mechanical energy and electricity. Those get inspected and refurbished on every overhaul as a matter of routine. On the Stennis, inspectors found one with damage beyond “normal wear and tear,” Naval Sea Systems Command spokesman Alan Baribeau told Stars and Stripes in 2024. The same thing turned up on the previous carrier through the yard, the USS George Washington.

Finding that on two carriers in a row is frankly the kind of bad luck you’d want to start planning for. To be fair, the Navy said it was studying exactly that kind of repeat problem so future contracts can line up parts earlier. Late materials and labor shortages made things worse on the Stennis too.

One more thing changed on this ship. She’s the first carrier to have all her sailors move off for the whole job, after a Navy probe found poor living conditions and commutes of up to three hours on the George Washington. That’s arguably an overdue fix. It also means the Navy is paying for extra months of off-ship housing every time the schedule moves.

First plan
Aug 2025
Original finish date, per USNI News.
Fiscal 2025 budget
Oct 2026
The date the Navy was still using in its 2024 dry dock release.
Fiscal 2026 budget
Nov 2027
Completion date in Navy documents, according to Janes.
ACTIVE
Days in the yard
2,008
Counted from May 6, 2021, to November 4, 2026.

Shortly, or November 2027?

So is she close to done?

Honestly, I don’t know, and the sources don’t line up.

Janes says the Navy’s fiscal 2026 budget included $483.1 million for cost growth and time-related charges after delivery moved back another 13 months. Add 13 months to October 2026 and you land right on Janes’ date for the work, “scheduled to be completed in November 2027.”

I tried to read the Navy’s budget book myself and it wouldn’t load, so I’m relying on Janes’ read of it. I also can’t tell you whether November 2027 means the day the Navy gets the ship back or the end of the funded work, and those might not be the same thing.

TWZ’s carrier tracker pulled the other way on October 27. It still gave October 2026 from budget documents, said “it’s unclear if that timeline will hold,” and pointed out that the Truman’s arrival suggests the Stennis is close to done. Which is a fair reading, since the yard wouldn’t normally start a second carrier on a whim.

You also can’t treat these budget dates like a train schedule. That same Janes report had the Truman starting in June 2026 and finishing in January 2031. She actually arrived on September 30, and the Navy now has her down for November 2031.

If I had to bet, I’d say the real answer lands somewhere between those two dates, but that’s a guess and you should read it as one. If November 2027 does hold, the Stennis would be at about six and a half years, compared with about six for the George Washington.

Who’s paying for all this?

You are, in case you were wondering.

Janes put the original contract at $2.9 billion, awarded in February 2021, while the Navy calls it a $3 billion contract. The Navy then asked for another $731.7 million in fiscal 2025 to cover the delay, followed by that $483.1 million in fiscal 2026. A public copy of the Pentagon’s fiscal 2027 weapons budget book lists “the cost to complete” and outfitting for the Stennis yet again, though I couldn’t find a Stennis-only number for that year.

“Time-related charges” sounds like jargon, but it’s basically the meter running. Keeping a job open costs money every month, whether or not anything new gets bolted on. I can’t find a current all-in total, and budget requests and contract values aren’t the same animal, so I’m not going to add these up and pretend that’s the final bill.

Long stays like this aren’t only an American problem, either. We recently looked at a British missile submarine that spent 89 months in an English yard getting a new reactor core.

What has to happen before she’s back in the fleet?

Sea trials are the big one. They’re pretty much the test drive for a ship, where the Navy and the yard take her out and make sure the reactors, the propulsion and everything else do what they’re supposed to at sea. The George Washington left Newport News for hers in late May 2023 and was handed back to the Navy within days, so you may not get much warning between the two.

The sailors also have to come back aboard. The Navy has set new living standards the ship has to meet before they can move aboard, USNI News reported in 2024. And handing her back doesn’t make her ready to fight, since a crew and an air wing still have to train up. Brandon Weichert of 19FortyFive argued on October 31 that she won’t deploy in early 2027, which is his opinion, though it seems pretty reasonable given all of the above.

The fleet could use her. TWZ counted three of the Navy’s carriers in maintenance as of October 27, and the USS Nimitz is due to retire next spring, once the new USS John F. Kennedy, which just caught its first F-35C, gets commissioned. Stars and Stripes expects that in March 2027.

I checked what the yard’s owner had to say too. HII’s quarterly earnings call on October 29 covered the Truman contract, valued at $5.1 billion, and the Stennis didn’t come up. I wouldn’t read much into that, since those calls are mostly about money coming in.

So as of November 4, there’s no announcement I can find of a departure, a handover or sea trials for the Stennis. The Truman, meanwhile, has been at the same yard since September 30, with her own redelivery scheduled for November 2031.

THE LOTvia The Lot

What do you think?

Sign in with Google when you post
ROOKIE›DRIVER›ENTHUSIAST›EXPERT›LEGEND ★
THE LOTOwner community
Visit →
Chema Bonilla Díaz

Chema Bonilla Díaz

Chema Bonilla covers the auto industry and mobility from Madrid, with a focus on new model launches, the arrival of emerging manufacturers in Europe, and the pace of electrification across the region. He trained in automotive technology before studying journalism at Universidad Francisco de Vitoria in Madrid, and has written for the Spanish motoring outlets Motorlife Magazine and Auto10.com. He also specializes in digital and social publishing. His beat gives AutoNotion readers a view of developments that hit Europe first: Chinese brands building out dealer networks, EV mandates already in force, and model launches that reach the US years later, if at all.
Contact: info@autonocion.com